Operations Management 9Th Edition By Heizer Render – Test Bank
To Purchase
this Complete Test Bank with Answers Click the link Below
https://tbzuiqe.com/product/operations-management-9th-edition-by-heizer-render-test-bank/
If face any problem or
Further information contact us At tbzuiqe@gmail.com
Sample
Test
CHAPTER 3: PROJECT MANAGEMENT
TRUE/FALSE
1. The ES of an
activity that has only one predecessor is simply the EF of that predecessor.
True (Determining the
project schedule, moderate)
2. One phase of a
large project is scheduling.
True (The importance
of project management, easy)
3. A project
organization works best for an organization when the project resides in only
one of its
functional areas.
False (Project
planning, moderate)
4. By their very
nature, projects have a limited lifetime, and that sets project management
apart from
the management of more
traditional activities.
True (Project
planning, moderate)
5. One responsibility
of a project manager is to make sure that the project meets its quality goals.
True (Project
planning, moderate)
6. Work Breakdown
Structure is a useful tool in project management because it addresses the
timing
of individual work
elements.
False (Project
planning, moderate)
7. Project managers
have their own code of ethics, established by the Project Management Institute.
True (Ethical issues
faced in project management, moderate) {AACSB: Ethical Reasoning}
8. Ethical issues
which can arise in projects include bid rigging, bribery, and “low balling.”
True (Ethical issues
faced in project management, easy) {AACSB: Ethical Reasoning}
9. Gantt charts give a
timeline for each of a project’s activities, but do not adequately show the
interrelationships of
activities.
True (Project
scheduling, moderate)
10. PERT, but not CPM,
has the ability to consider the precedence relationships in a project.
False (Project
scheduling, moderate)
11. The shortest of
all paths through the network is the critical path.
False (Project
management techniques: PERT and CPM, moderate)
12. The fundamental
difference between PERT and CPM is that PERT uses the beta distribution for
crashing projects
while CPM uses cost estimates.
False (Project
management techniques: PERT and CPM, moderate)
13. Slack is the
amount of time an activity can be delayed without delaying the entire project.
True (Project
management techniques: PERT and CPM, moderate)
37
14. Every network has
at least one critical path.
True (Project
management techniques: PERT and CPM, moderate)
15. The critical path
can be determined by use of either the “forward pass” or the “backward pass.”
False (Project
management techniques: PERT and CPM, moderate)
16. The PERT
pessimistic time estimate is an estimate of the minimum time an activity will
require.
False (Project
management techniques: PERT and CPM, easy)
17. The standard
deviation of project duration is the average of the standard deviation of all
activities
on the critical path.
False (Project
management techniques: PERT and CPM, moderate)
18. In PERT analysis, the
identification of the critical path can be incorrect if a noncritical activity
takes substantially
more than its expected time.
True (Project
management techniques: PERT and CPM, difficult)
19. Shortening the
project’s duration by deleting unnecessary activities is called “project
crashing.”
False (Cost-time
trade-offs and project crashing, moderate)
20. In project
management, crashing an activity must consider the impact on all paths in the
network.
True (Cost-time
trade-offs and project crashing, moderate)
MULTIPLE CHOICE
21. Which of the
following statements regarding Bechtel is true?
a. Its competitive
advantage is project management.
b. Bechtel was the
construction contractor for the Hoover Dam.
c. While helping to
rebuild Iraq, Bechtel’s crews had to travel under armed escort.
d. Bechtel’s
procurement program is global in nature.
e. All of the above
are true.
e (Global company
profile, easy)
22. Which of the
following statements about Bechtel is true?
a. Even though Bechtel
is over 100 years old, the Kuwaiti oil fields was its first “project.”
b. Bechtel is the
world’s premier manager of massive construction and engineering projects.
c. Bechtel’s
competitive advantage is supply chain management.
d. While its projects
are worldwide, its network of suppliers is largely in the U.S.
e. All of the above
are true.
b (Global company
profile, moderate)
23. The phases of
project management are
a. planning,
scheduling, and controlling
b. planning,
programming, and budgeting
c. planning,
organizing, staffing, leading, and controlling
d. different for
manufacturing projects than for service projects
e. GANTT, CPM, and
PERT
a (The importance of
project management, easy)
38
24. A project
organization
a. is effective for
companies with multiple large projects
b. is appropriate only
in construction firms
c. often fails when
the project cuts across organizational lines
d. is formed to ensure
that programs (projects) get proper management and attention
e. a and d are both
true
e (Project planning,
moderate)
25. Which of the
following statements regarding project management is false?
a. Gantt charts give a
timeline for each of a project’s activities, but do not adequately show the
interrelationships of
activities.
b. A project
organization works best for a project that is temporary but critical to the
organization.
c. Project
organization works well when the work contains simple, independent tasks.
d. Gantt charts and
PERT/CPM are never used together.
e. None of the above
is true.
c (Project planning,
moderate)
26. A code of ethics
especially for project managers
a. has been
established by the Project Management Institute
b. has been formulated
by the Federal government
c. has been formulated
by the World Trade Organization
d. is inappropriate,
since everyone should use the same guidance on ethical issues
e. does not exist at
this time
a (Project planning,
moderate) {AACSB: Ethical Reasoning}
27. Divulging
information to some bidders on a project to give them an unfair advantage
a. is the same thing
as altering a status report
b. is bribery
c. is permitted by
NAFTA
d. is known as bid
rigging
e. is acceptable for
private corporations but not for government agencies
d (Project planning,
moderate) {AACSB: Ethical Reasoning}
28. Ethical issues
that may arise in projects large and small include
a. bid rigging
b. expense account
padding
c. compromised safety
or health standards
d. bribery
e. All of the above
are true.
e (Project planning,
easy) {AACSB: Ethical Reasoning}
29. Which of the
following statements regarding Gantt charts is true?
a. Gantt charts give a
timeline and precedence relationships for each activity of a project.
b. Gantt charts use
the four standard spines of Methods, Materials, Manpower, and Machinery.
c. Gantt charts are
visual devices that show the duration of activities in a project.
d. Gantt charts are
expensive.
e. All of the above
are true.
c (Project scheduling,
moderate)
39
30. Which of the
following statements regarding critical paths is true?
a. The shortest of all
paths through the network is the critical path.
b. Some activities on
the critical path may have slack.
c. Every network has
exactly one critical path.
d. On a specific
project, there can be multiple critical paths, all with exactly the same
duration.
e. The duration of the
critical path is the average duration of all paths in the project network.
d (Project management
techniques: PERT and CPM, moderate)
31. Which of the
following statements regarding CPM is true?
a. The critical path
is the shortest of all paths through the network.
b. The critical path
is that set of activities that has positive slack.
c. Some networks have
no critical path.
d. All activities on
the critical path have their LS equal their predecessor’s EF.
e. All of the above
are false.
d (Project management
techniques: PERT and CPM, moderate)
32. A simple CPM
network has three activities, A, B, and C. A is an immediate predecessor of B
and
of C. B is an
immediate predecessor of C. The activity durations are A=4, B=3, C=8.
a. The critical path
is A-B-C, duration 15.
b. The critical path
is A-C, duration 12.
c. The critical path
is A-B-C, duration 13.5
d. The critical path
cannot be determined without knowing PERT expected activity times.
e. The network has no
critical path.
a (Project management
techniques: PERT and CPM, difficult) {AACSB: Analytic Skills}
33. A simple CPM
network has three activities, D, E, and F. D is an immediate predecessor of E
and of
F. E is an immediate
predecessor of F. The activity durations are D=4, E=3, F=8.
a. The critical path
is D-E-F, duration 15.
b. The critical path
is D-F, duration 12.
c. Slack at D is 3
units
d. Slack at E is 3
units
e. Both a and c are
true
a (Project management
techniques: PERT and CPM, difficult) {AACSB: Analytic Skills}
34. A simple CPM
network has five activities, A, B, C, D, and E. A is an immediate predecessor
of C
and of D. B is also an
immediate predecessor of C and of D. C and D are both immediate
predecessors of E.
a. There are two paths
in this network.
b. There are four
paths in this network.
c. There are five
paths in this network.
d. There are 25 paths
through this network.
e. None of these
statements is true.
b (Project management
techniques: PERT and CPM, moderate) {AACSB: Analytic Skills}
40
35. Activity D on a
CPM network has predecessors B and C, and has successor F. D has duration 6.
B’s
earliest finish is 18,
while C’s is 20. F’s late start is 26. Which of the following is true?
a. B is a critical
activity.
b. C is completed
before B.
c. D has no slack but
is not critical.
d. D is critical, and
has zero slack.
e. All of the above
are true.
d (Project management
techniques: PERT and CPM, difficult) {AACSB: Analytic Skills}
36. Which of the
following statements regarding CPM networks is true?
a. There can be
multiple critical paths on the same project, all with different durations.
b. The early finish of
an activity is the latest early start of all preceding activities.
c. The late start of
an activity is its late finish plus its duration.
d. If a specific
project has multiple critical paths, all of them will have the same duration.
e. All of the above
are true.
d (Project management
techniques: PERT and CPM, moderate)
37. Activity M on a
CPM network has predecessors N and R, and has successor S. M has duration 5.
N’s late finish is 18,
while R’s is 20. S’s late start is 14. Which of the following is true?
a. M is critical and
has zero slack.
b. M has no slack but
is not critical.
c. The last start time
of S is impossible.
d. N is a critical
activity.
e. S is a critical
activity.
c (Project management techniques:
PERT and CPM, difficult) {AACSB: Analytic Skills}
38. Which of the
following statements concerning CPM activities is false?
a. The early finish of
an activity is the early start of that activity plus its duration.
b. The late finish is
the earliest of the late start times of all successor activities.
c. The late start of
an activity is its late finish less its duration.
d. The late finish of
an activity is the earliest late start of all preceding activities.
e. The early start of
an activity is the latest early finish of all preceding activities.
d (Project management
techniques: PERT and CPM, difficult)
39. The time an
activity will take assuming very unfavorable conditions is
a. the optimistic time
b. the pessimistic
time
c. the activity variance
d. the minimum time
e. exactly twice as
long as the expected time
b (Project management
techniques: PERT and CPM, moderate)
41
40. The critical path
for the network activities shown below is _____ with duration ______.
Activity Duration Immediate
Predecessors
A 4 —
B 2 A
C 7 —
D 4 A
E 5 B,C,D
a. A-B-D; 10
b. A-B-E; 11
c. C-E; 12
d. A-D-E; 13
e. A-B-C-D-E; 22
d (Project management
techniques: PERT and CPM, difficult) {AACSB: Analytic Skills}
41. The critical path
for the network activities shown below is _____ with duration ______.
Activity Duration
Immediate
Predecessors
A 2 —
B 4 —
C 6 A,B
D 1 A,B
E 2 B,C,D
a. A-D-E; 5
b. B-E; 6
c. B-D-E; 7
d. A-C-E; 10
e. B-C-E; 12
e (Project management
techniques: PERT and CPM, difficult) {AACSB: Analytic Skills}
42. The _____
distribution is used by PERT analysis to calculate expected activity times and
variances.
a. Normal
b. Beta
c. Alpha
d. Gaussian
e. Binomial
b (Project management
techniques: PERT and CPM, easy)
42
43. The expected
activity time in PERT analysis is calculated as
a. the simple average
of the optimistic, pessimistic, and most likely times
b. the weighted
average of a, m, and b, with m weighted 4 times as heavily as a and b
c. the sum of the
optimistic, pessimistic, and most likely times
d. the sum of the
optimistic, pessimistic, and most likely times, divided by six
e. the sum of the
activity variances, divided by six
b (Project management
techniques: PERT and CPM, moderate)
44. The critical path
for the network activities shown below is _____ with duration ______.
Activity Duration
Immediate
Predecessors
A 10 —
B 8 —
C 2 A
D 4 A
E 5 B,C, D
a. A-C; 12
b. A-D-E; 19
c. B-E; 13
d. A-B-C-D-E; 29
e. none of the above
b (Project management
techniques: PERT and CPM, difficult) {AACSB: Analytic Skills}
45. Which of the
following statements regarding PERT times is true?
a. The optimistic time
estimate is an estimate of the minimum time an activity will require.
b. The optimistic time
estimate is an estimate of the maximum time an activity will require.
c. The probable time
estimate is calculated as t = (a + 4m + b).
d. Pessimistic time
estimate is an estimate of the minimum time an activity will require.
e. Most likely time
estimate is an estimate of the maximum time an activity will require.
a (Project management
techniques: PERT and CPM, moderate)
46. Which of the
following statements regarding PERT times is true?
a. Expected time is an
estimate of the time an activity will require if everything goes as planned.
b. The optimistic time
estimate is an estimate of the maximum time an activity will require.
c. The probable time
estimate is calculated as t = (a + 4m + b)/6.
d. Pessimistic time
estimate is an estimate of the minimum time an activity will require.
e. Most likely time
estimate is an estimate of the maximum time an activity will require.
c (Project management
techniques: PERT and CPM, moderate)
47. The Beta
distribution is used in project management to
a. calculate slack on
activities not on the critical path
b. calculate the
probability that a project will be completed within its budget
c. calculate
pessimistic and optimistic activity times
d. determine which
activity should be crashed
e. none of the above
e (Project management
techniques: PERT and CPM, moderate)
43
48. The Beta distribution
is used in project management to
a. determine which
activity should be crashed
b. calculate the
probability that a project will be completed within its budget
c. calculate expected
activity times
d. calculate slack for
activities on the critical path
e. none of the above
c (Project management
techniques: PERT and CPM, moderate)
49. In a PERT network,
non-critical activities that have little slack need to be monitored closely
a. because PERT treats
all activities as equally important
b. because
near-critical paths could become critical paths with small delays in these
activities
c. because slack is
undesirable and needs to be eliminated
d. because they are
causing the entire project to be delayed
e. because they have a
high risk of not being completed
b (Project management
techniques: PERT and CPM, moderate)
50. Which of the
following statements regarding PERT analysis is true?
a. Each activity has
two estimates of its duration.
b. Project variance is
the sum of all activity variances.
c. Project standard
deviation is the sum of all critical activity standard deviations.
d. Only critical
activities contribute to the project variance.
e. None of the above
is true.
d (Project management
techniques: PERT and CPM, moderate)
51. A project being analyzed
by PERT has 60 activities, 13 of which are on the critical path. If the
estimated time along
the critical path is 214 days with a project variance of 100, the probability
that
the project will take
224 days or more to complete is
a. near zero
b. 0.0126
c. 0.1587
d. 0.8413
e. 2.14
c (Project management
techniques: PERT and CPM, moderate) {AACSB: Analytic Skills}
52. An activity on a
PERT network has these time estimates: optimistic = 2, most likely = 5, and
pessimistic = 10. Its
expected time is
a. 5
b. 5.33
c. 5.67
d. 17
e. none of these
b (Project management
techniques: PERT and CPM, moderate) {AACSB: Analytic Skills}
44
53. An activity on a
PERT network has these time estimates: optimistic = 1, most likely = 2, and
pessimistic = 5. Its
expected time is
a. 2
b. 2.33
c. 2.67
d. 8
e. none of these
b (Project management
techniques: PERT and CPM, moderate) {AACSB: Analytic Skills}
54. An activity on a
PERT network has these time estimates: optimistic = 2, most likely = 3, and
pessimistic = 8. Its expected
time and variance (if it is a critical activity) are
a. 3.67; 1
b. 3.67; 6
c. 4.33; 1
d. 4.33; 6
e. none of these
a (Project management
techniques: PERT and CPM, moderate) {AACSB: Analytic Skills}
55. A local project
being analyzed by PERT has 42 activities, 13 of which are on the critical path.
If
the estimated time
along the critical path is 105 days with a project variance of 25, the
probability
that the project will
be completed in 95 days or less is
a. -0.4
b. 0.0228
c. 0.3444
d. 0.9772
e. 4.2
b (Project management
techniques: PERT and CPM, moderate) {AACSB: Analytic Skills}
56. A project being
analyzed by PERT has 38 activities, 16 of which are on the critical path. If
the
estimated time along
the critical path is 90 days with a project variance of 25, the probability
that
the project will be
completed in 88 days or less is
a. 0.0228
b. 0.3446
c. 0.6554
d. 0.9772
e. 18
b (Project management
techniques: PERT and CPM, moderate) {AACSB: Analytic Skills}
57. A PERT project has
45 activities, 19 of which are on the critical path. The estimated time for the
critical path is 120
days. The sum of all activity variances is 64, while the sum of variances along
the critical path is
36. The probability that the project can be completed between days 108 and 120
is
a. -2.00
b. 0.0227
c. 0.1058
d. 0.4773
e. 0.9773
d (Project management
techniques: PERT and CPM, difficult) {AACSB: Analytic Skills}
45
58. A contractor’s
project being analyzed by PERT has an estimated time for the critical path of
120
days. The sum of all
activity variances is 81; the sum of variances along the critical path is 64.
The
probability that the
project will take 130 or more days to complete is
a. 0.1056
b. 0.1335
c. 0.8512
d. 0.8943
e. 1.29
a (Project management
techniques: PERT and CPM, moderate) {AACSB: Analytic Skills}
59. Analysis of a PERT
problem shows the estimated time for the critical path to be 108 days with a
variance of 64. There
is a .90 probability that the project will be completed before approximately
day ______.
a. 98
b. 108
c. 109
d. 115
e. 118
e (Project management
techniques: PERT and CPM, difficult) {AACSB: Analytic Skills}
60. A project whose
critical path has an estimated time of 120 days with a variance of 100 has a
20%
chance that the
project will be completed before day ______ (rounded to nearest day).
a. 98
b. 112
c. 120
d. 124
e. 220
b (Project management
techniques: PERT and CPM, difficult) {AACSB: Analytic Skills}
61. A project whose
critical path has an estimated time of 820 days with a variance of 225 has a
20%
chance that the
project will be completed before day ______ (rounded to nearest day).
a. 631
b. 689
c. 807
d. 833
e. 1009
c (Project management
techniques: PERT and CPM, difficult) {AACSB: Analytic Skills}
62. Contract
requirements state that a project must be completed within 180 working days, or
it will
incur penalties for
late completion. Analysis of the activity network reveals an estimated project
time of 145 working
days with a project variance of 400. What is the probability that the project
will be completed
before the late-payment deadline?
a. 0.0401
b. 0.4599
c. 0.8056
d. 0.9599
e. near 1.0000, or
almost certain
d (Project management
techniques: PERT and CPM, difficult) {AACSB: Analytic Skills}
46
63. Which of these
statements regarding time-cost tradeoffs in CPM networks is true?
a. Crashing is not
possible unless there are multiple critical paths.
b. Crashing a project
often reduces the length of long-duration, but noncritical, activities.
c. Activities not on
the critical path can never be on the critical path, even after crashing.
d. Crashing shortens
the project duration by assigning more resources to one or more of the
critical tasks.
e. None of the above
is true.
d (Cost-time
trade-offs and project crashing, moderate)
64. What was the name
of the construction project to rebuild the Pentagon after the terrorist attacks
on
Sept. 11, 2001?
a. Project Panther
b. Project Pit Bull
c. Project Python
d. Project Piranha
e. Project Phoenix
e (Project management
techniques: PERT and CPM, moderate)
65. Which of the
following statements regarding time-cost tradeoffs in CPM networks is false?
a. “Project Crashing”
shortens project duration by assigning more resources to critical tasks.
b. Crashing sometimes
has the reverse result of lengthening the project duration.
c. Crashing must
consider the impact of crashing an activity on all paths in the network.
d. Activities not on
the critical path can become critical after crashing takes place.
e. All of the above
are true.
b (Cost-time
trade-offs and project crashing, moderate)
66. If an activity
whose normal duration is 13 days can be shortened to 10 days for an added cost
of
$1,500, the crash cost
per period is
a. $500
b. $750
b. $1,500
d. $13,000
e. $15,000
a (Cost-time
trade-offs and project crashing, moderate) {AACSB: Analytic Skills}
47
67. Two activities are
candidates for crashing on a CPM network. Activity details are in the table
below. To cut one day
from the project’s duration, activity _____ should be crashed first, adding
______ to project
cost.
Activity Normal Time
Normal Cost Crash Duration Crash Cost
One 8 days $6,000 6
days $6,800
Two 10 days $4,000 9
days $5,000
a. One; $400
b. One; $6,800
c. Two; $1,000
d. Two; $5,000
e. One or two should
be crashed; $1,400
a (Cost-time
trade-offs and project crashing, moderate) {AACSB: Analytic Skills}
68. If an activity
whose normal duration is 15 days can be shortened to 10 days for an added cost
of
$2,000, the crash cost
per period is
a. $400
b. $2,000
c. $10,000
d. $20,000
e. $30,000
a (Cost-time
trade-offs and project crashing, moderate) {AACSB: Analytic Skills}
69. A network has been
crashed to the point where all activities are critical. Additional crashing
a. is unnecessary
b. is impossible
c. is prohibitively
expensive
d. may require
crashing multiple tasks simultaneously
e. can be done, but
all critical tasks must be reduced in duration
d (Cost-time
trade-offs and project crashing, moderate)
48
70. Two activities are
candidates for crashing on a CPM network. Activity details are in the table
below. To cut one day
from the project’s duration, activity _____ should be crashed first, adding
______ to project
cost.
Activity Normal Time
Normal Cost Crash Duration Crash Cost
B 4 days $6,000 3 days
$8,000
C 6 days $4,000 4 days
$6,000
a. B; $2,000
b. B; $8,000
c. C; $1,000
d. C; $2,000
e. C; $6,000
Comments
Post a Comment